Fast learning
Have you ever dreamed about passing the exam (with 070-178 test guide: Microsoft Project 2010, Managing Projects) as well as getting the relevant certification with preparation only for two or three days? This sounds almost impossible in the past, but now our 070-178 exam torrent materials are here for you to achieve your dream. Since our practice test materials are compiled by the top Microsoft experts around the world, the contents in the 070-178 training materials are definitely quintessence for the exam, which covers all of the key points as well as the latest information about the events happened in the field recently.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
High pass rate
There is no doubt that high pass rate is our eternal pursuit, and the pass rate is substantially based on the quality of the study material, as I mentioned just now, our 070-178 test guide: Microsoft Project 2010, Managing Projects own the highest quality in this field, so it is naturally for us to get the highest pass rate in this field. Now we have the data to show that the pass rate among the workers in this field who have bought our 070-178 exam torrent as well as having practiced all of the questions in our practice test materials has reached as high as 98% to 100%. In other words, almost all of our customers of 070-178 training materials have passed the exam as well as getting the related certification. You really can trust us completely.
It is quite apparent that the exam in Microsoft field is too hard for the majority of workers to pass because there are a lot of eccentric questions in the exam, however, just like the old saying goes: Where there is a will, there is a way. You really should spare no effort to have a try as long as you are still eager to get promoted as well as a raise in pay. It is of great significance for you to be more successful in your field (070-178 test guide: Microsoft Project 2010, Managing Projects). If you are still afraid about the results in the exam, our company is willing to offer you the sincerest help--our 070-178 exam torrent. Now I will show you some of the shinning points about our 070-178 training materials for you.
Protect the interests of customers
Our company holds the running idea that our customers' profits prevails over our company's own profits (070-178 test guide: Microsoft Project 2010, Managing Projects), so we will do everything in the interests of our customers. On the one hand, we will do our utmost to protect your personal information. Our intelligent operating system will encrypt all of your information as soon as you pay for the 070-178 exam torrent materials in this website. On the other side, even though the pass rate among our customers with the guidance of our 070-178 training materials has reached nearly 100%, nevertheless, it is inevitable that there are still some people would worry about it, if you still have any misgiving, I can promise you that you can get full refund of our Microsoft Project 2010, Managing Projects dumps torrent materials if you failed in the exam, but the truth is that it is almost impossible for you to fail the exam as long as you use our practice test materials.
Microsoft Project 2010, Managing Projects Sample Questions:
1. You need to ensure that you can view only the tasks on your projects critical path. What should you do?
A) View the projects Gantt chart and apply the Critical group.
B) On the Advanced tab of the Project 2010 options, select the Calculate multiple critical paths check box.
C) On the Advanced tab of the Project 2010 options, modify the Tasks are critical if slack is less than or equal to option.
D) View the project's Gantt chart and apply the Critical filter.
2. The first major phase of your project is scheduled for a duration of 45 days. However, you do not have task information for other phases. You need to indicate that the duration of the entire project is 200 days. What should you do?
A) Create a manually scheduled summary task.
B) Select the Summary Tasks option.
C) Update the project calendar.
D) Select the Project Summary Task option.
3. You have a task named Tasks that has a duration of four days and a finish-to-finish relationship with a task named Task4. You need to reconfigure Tasks to be a milestone. You also need to retain the original duration and resource assignments. You select Tasks. What should you do next?
A) Select the Mark Task as Milestone check box.
B) Remove the predecessor assignments.
C) Click the Insert Milestone button.
D) Change Work to zero hours.
4. You need to view Task ID 0 on your project plan. What should you do?
A) Insert a new Summary Task.
B) On the Format tab, select Project Summary Task.
C) On the Format tab, select Summary Tasks.
D) On the Advanced tab of the Project 2010 options, select Show Status Bar.
5. The milestones in your project schedule represent the end of phases. You need to change the background color of the cells of the milestones to blue. What should you do on the Format tab?
A) Select Bar Styles, and then select Milestone.
B) Select Drawing, and then select Text Box.
C) Select Layout, and then select Show drawings.
D) Select Text Styles, and then select Milestone Tasks.
E) Select Column Settings, and then select Milestone.
Solutions:
Question # 1 Answer: D | Question # 2 Answer: A | Question # 3 Answer: A | Question # 4 Answer: B | Question # 5 Answer: D |