NEW QUESTION # 153
What is a likely benefit of re-estimating throughout the project life cycle?
- A. Overall project duration is reduced.
- B. The project will be much more economically viable.
- C. Reduction in contingency reserves are achieved.
- D. The business case is justified to a greater degree.
Answer: C
NEW QUESTION # 154
Which one of the following illustrates why effective project management is beneficial to an organisation?
- A. It utilises resources as and when required under direction of a project manager.
- B. It recommends using only highly skilled people in the project team.
- C. It advocates employing A. consultancy firm which specialises in managing change.
- D. It ensures that the chief executive is accountable for the achievement of the defined benefits.
Answer: A
NEW QUESTION # 155
What is the term given to the senior management team that set the strategic. direction for a project?
- A. Project management office.
- B. Project steering group.
- C. Programme director.
- D. Change control board.
Answer: C
NEW QUESTION # 156
What is essential for ensuring the level of stakeholder engagement is maintained throughout the delivery of the project?
- A. The project management plan is established.
- B. All stakeholders are treated equally.
- C. Stakeholders communicate with each other.
- D. An effective communication plan is used.
Answer: D
NEW QUESTION # 157
What aspect is important to clarify when conducting scope definition?
- A. Who is going to perform the work.
- B. When the work is going to be performed.
- C. The boundaries and interfaces with adjacent projects.
- D. The number of products contained in the PBS,
Answer: C
NEW QUESTION # 158
Which of the following statements describes a key difference between quality assurance and quality control?
- A. Quality control is about fitness for purpose whilst quality assurance is about management confidence.
- B. Quality control is about fitness for purpose whilst quality assurance is about testing.
- C. Quality control is about management whilst quality assurance is about controlling change.
- D. Quality control is about testing whilst quality assurance is about planning.
Answer: A
NEW QUESTION # 159
Suppliers are stakeholders of a project management plan because they:
- A. provide acceptance certificates based on quality of resources supplied.
- B. determine the quality requirements of goods supplied.
- C. help satisfy the project's resource requirements.
- D. contribute to the project's procurement strategy.
Answer: C
NEW QUESTION # 160
The primary purpose of a milestone in a project is to show:
- A. resource constraints.
- B. task dependencies.
- C. critical path highlights.
- D. significant events.
Answer: D
NEW QUESTION # 161
We have an expert-written solution to this problem!
Who has ultimate responsibility for project risk?
- A. Steering group.
- B. Risk owner.
- C. Project sponsor.
- D. Project manager
Answer: C
NEW QUESTION # 162
A work breakdown structure shows the levels of work required to produce the deliverables for the project in what type of diagram?
- A. Histogram.
- B. Historical.
- C. Hierarchical.
- D. Handover.
Answer: C
NEW QUESTION # 163
Project risk management is best described as:
- A. managing responses to threats.
- B. identifying and acknowledging threats and opportunities.
- C. minimising threats and maximising opportunities.
- D. planning responses to threats.
Answer: C
NEW QUESTION # 164
Which of the following is not a key aspect of issue resolution?
- A. Apply change control.
- B. Assign actions to relevant team member.
- C. Escalate analysis to project sponsor.
- D. Increase risk budget.
Answer: D
NEW QUESTION # 165
The concept that describes how estimating accuracy changes through the project life cycle is termed:
- A. estimating risk.
- B. parametric estimating.
- C. estimating funnel.
- D. normal values.
Answer: C
NEW QUESTION # 166
A project manager requires a team member to focus on the team's objectives and draw out other team members. Which of the Belbin's team roles is most appropriate?
- A. Monitor evaluator.
- B. Specialist.
- C. Co-ordinator
- D. Shaper.
Answer: C
NEW QUESTION # 167
Which of the following statements refers to how scope is managed in a linear project but not an iterative project?
- A. The scope of work is the starting point for the implementation of change control.
- B. Teams can re-prioritise requirements within the scope.
- C. Teams can act on new knowledge to change the scope.
- D. Scope definition is assumed to be fixed for the whole project
Answer: D
NEW QUESTION # 168
Quality control consists of:
1) improvement
2) inspection
3) measurement
4) testing
- A. 1, 2 and 4
- B. 2, 3 and 4
- C. 1, 3 and 4
- D. 1, 2 and 3
Answer: B
NEW QUESTION # 169
Which structure shows the reporting relationships and communications channels for a project?
- A. Organisational Breakdown Structure.
- B. Responsibility assignment structure.
- C. Work Breakdown Structure.
- D. Product Breakdown Structure.
Answer: A
NEW QUESTION # 170
While carrying out quality management for the project, you have been assigned the task of determining the quality standards that are applicable and how they should apply. Which part of quality management would best describe this activity?
- A. Total quality.
- B. Quality planning.
- C. Quality control.
- D. Quality assurance.
Answer: B
NEW QUESTION # 171
What is the main benefit of using prototyping. time boxing or iterative thinking?
- A. Try allow the project to develop an extended life cycle.
- B. They always deliver the project quicker than planned
- C. They offer tested methods for experimentation and risk reduction
- D. They reduce stakeholders' expectations of how they benefit from the project.
Answer: C
NEW QUESTION # 172
What is the best way that PESTLE analysis supports the development of a business case?
- A. It provides A. powerful way in which the most favourable financial returns are shown from the project options being considered.
- B. It considers a number of options avoiding over reliance on a single idea, when there may be other more favourable options available.
- C. It identifies which tools and techniques are necessary in order to arrive at the best group of projects to be considered as valid options.
Answer: B
Explanation:
D It shows which assets, capabilities, processes and functions are required to be included in the business case.
NEW QUESTION # 173
The main purpose of configuration management is to:
- A. provide control of the deliverables and avoid mistakes or misunderstandings.
- B. maximise the impact of agreed enhancements on the project deliverables.
- C. ensure that the final product meets the strategic needs of the business.
- D. minimise the impact of changes on the scope of the project.
Answer: A
NEW QUESTION # 174
Scheduling can best be defined as the process used to determine:
- A. sub-contractor's responsibilities
- B. overall project duration.
- C. project cost estimating.
- D. the project management plan.
Answer: B
NEW QUESTION # 175
What could be considered a significant barrier to communication?
- A. Attitudes, emotions and prejudices.
- B. Use of informal communication channels
- C. Having formal meetings.
- D. Use of body language.
Answer: A
NEW QUESTION # 176
......